06 February 2016 – Recent Framing Progress at Copperwood includes completion of main level floor decking and heavy timber columns. Seven-person crew is making short work of it. This week we received delivery of steel columns for main west-side canopy + special lumber order from American Pole & Timber which includes the 32′ long treated true 2×12 roof rafters and the timber for front entry bridge and extended Airstream canopy. We expect shell to be weathered-in by late February 2016. See project portfolio here.